§ 123-6 - Full Review.

§ 123-6 - Full Review.

The application for a Full Review shall be made to the Planning Board. The applicant shall follow the process specified in Section 123-7 through Section 123-18 of this Chapter. In the case of approved Full Review applications, approved plans shall be signed and recorded at the Registry of Deeds. The following shall apply:

  1. Submit to the Planner a complete application as defined in Article V. Applicants are advised to utilize this checklist themselves to avoid submitting incomplete applications which will cause delays. Note that other governmental approvals must be applied for at the time of application submission, though the actual permit or approval may be a condition of Site Plan Review approval.
  2. Plans and plats shall be prepared by New Hampshire licensed surveyors and possibly professional engineers for a Full Review Application. The following are the standards which shall be met:
    1. Sheet Size. Sheet size shall not exceed 24" by 36".
    2. Scale. The scale of all plats shall be at least 1" = 40' or larger (e.g. 1”=30’; 1”=20’, etc.).
    3. Supplemental Plans. In the event that there are plan sheets accompanying the primary site plan plat, and because only the plat will be recorded at the Registry of Deeds, all supplemental plan sheets shall be referenced by title and latest date of revision on the plat to be recorded.
    4. NH Licensed Surveyors and Professional Engineers. The detailed boundary survey and other related survey information including but not limited to setbacks, building locations and topography, shall be certified by a NH licensed surveyor regarding its accuracy. Road design, drainage, and floodplain construction shall be certified by a NH licensed professional engineer to meet all applicable standards and regulations. Certification shall be indicated on plans by professional stamp and the accompanying signature. In all cases, the plat to be recorded shall be certified by the surveyor and/or professional engineer.
  3. The Planner shall prepare a written review of the application and provide it to the Planning Board one week prior to application acceptance. The Planner shall be responsible for obtaining the input of other Town staff. Applicants may pick up at Town Hall a copy of the written review as soon as it is available to the Board.
  4. The Planning Board should conduct a site visit prior to application approval. When possible, this site visit shall precede application acceptance to ensure that the Board is familiar with the site prior to any discussions.
Full Review.

part number

123-6